Case Studies

Back to case study index...   |   Next Case Study


CERRITOS CIVIC CENTER PARKING STRUCTURE
Innovative Painting & Waterproofing Inc.





PROJECT OUTLINE:
• At-grade top deck with multiple levels
below grade

• All concrete construction with reinforcing
steel

• Heavy traffic – located in central plaza
at City Hall, main library, sheriff ’s/
community service station, dolphin
fountain water recreation area, park-like
art gallery and near Cerritos Center for
the Performing Arts.

• Top deck and ramp suffered from extensive
cracks with multiple leaks onto lower
levels. Several years of attempted repair
via crack chasing and caulking, urethane
foam grout injection and other methods
had been used for spot repairs.

• 80,000 square feet slated for complete
removal of existing urethane deck coating,
abrasive blasting, concrete repair and
installation of a polyurea deck coating
system.

• Extensive site coordination – because it is
the only parking at the civic center other
than one small lot next to the structure,
lower levels had to be accessible with
one driveway and half the ramp open
at all times, and parking coordinated to
keep vehicles away from the work areas
especially during spray operations.

• Very tight schedule – 30 working days
maximum.

The Cerritos Civic Center Parking Structure is the central transportation hub for the Civic Center. Approximately 20 years old, the top deck is at-grade with
additional levels below grade. Originally coated with a urethane deck coating, years of exposure, traffic, vibration, earthquakes and soft settling had taken their toll. Many voids had appeared in the top deck and upper ramp, with continuous water leakage problems due to rain and surface washdowns. Multiple repairs had been made over the years, including crack-chasing with sealant installation, urethane foam grout injection and surface patching, all with some level of success. It was finally determined by City Engineers that in the long-term, installation of a new coating on the exposed surfaces coupled with crack repair would be the most cost-effective solution.



The project was originally slated for a urethane system, but after consulting with Donald Dancey, President of Innovative Painting & Waterproofing, (who had performed much of the previous repair work) the City brought in Polycoat Products for an assessment of the structure. Polycoat’s inspection resulted in recommendation of a Polyurea-based membrane system with a urethane finish due to very short recoat times, extremely high tensile strength, high longation and superior integrated film bonding and toughness. With the critical issues of limited work periods, short project time window, and need for availability of portions of the structure at all times, polyurea was selected for the project due to its combination of durability and speed of application.

With the notice to proceed issued July 5th 2006 and a completion target of August 16, 2006, Innovative’s crew of specially-trained applicators and mechanics went to work. A master logistics plan was laid out by Jim Sliff, Innovative’s Vice President and City Project Engineer Fredy Bonilla, with specific sections slated for “locked in” time periods; this was critical as all City departments and the residents had to be notified of access routes and limitations.



Preparation consisted of use of up to four “Terminator” coating removal units
at one time, closely followed by grinders and shotblasting. As areas were stripped and prepared, Innovative’s team of concrete repair specialists immediately followed with a mix of epoxy/aggregate blends and polyurea sealant to renew the deck for coating. As quickly as repairs were cured, surfaces were primed with Series 21 Epoxy Primer. Then the major water intrusion system was installed – Series 5502 Aromatic Polyurea, applied by high-temperature, high-pressure plural-component spray using Graco EXP-2 Reactor pumps (with feed pumps, electrical power, air compressor and
repair/maintenance shop all enclosed in a trailer with the EXP-2) and Fusion guns.

With the quick-set properties of fastset aromatic polyurea, it was possible to
immediately follow with a coat of mediumset Polyurea, a slightly slower-curing system specifically chosen for aggregate broadcast embedment. #16 aggregate was blown onto the surface using a technique specifically developed for the project – employing hopper-type texture guns to disperse
aggregate over the surface in a uniform manner at 5 times the speed of a normal hand broadcast.



With the “slow cure” 6881 drying in a matter of 15-20 minutes, a finish coat of
Polyglaze 100 was quickly applied; at turn radii and other high-wear areas, a second aggregate broadcast and final coat of Polyglaze was applied. The area was then finished with line striping and epoxy setting of concrete parking bumpers. As each area was completed, it was opened up to traffic and another area underwent the identical process. With the critical time window, a large, cross-trained crew, backup equipment, and equipment support were vital in meeting project goals. The project was literally completed right on time, with the City receiving a showpiece parking deck worthy of the beauty and utility of the Civic Center.










PDA - Join now!

CONTACT PDA   |   MEET PDA   |   RESOURCES   |   BENEFITS   |   PDA NEWS   |   EDUCATION & CONFERENCES

Copyright © 2007 PDA   |   Privacy Statement / Legal
choose language