Point of Interest:
Primers, sealants, putty, spray polyurea coatings
and linings
Project:
Concrete audience stands coated with grey, green and blue polyurea elastomer
at a thickness of 1.5mm (59 mils) for decorative and waterproofing use.
It is over 200, 000 square meters (2.15 million ft2).
Designed substrate round corners with a radius of 20 - 30mm (0.8 – 1.2 in).
Over 350 tons polyurea was sprayed (~85,700 gallons).
Problems & Challenges:
Designed round corner on audience stand stairs.
Anti-yellowing system for long term sunshine exposure.
Scope of Work:
Audience Stand with Grey, blue and green polyurea elastomer applied
at 2mm (80 mils).
Site Challenges & Unforeseen Issues:
This project took 1.5 years to complete with temperature lower at -20°C (-4°F)
and humidity higher than 95%.
Concrete surface were very rough and numerous defects.
Project Status:
The 29th Beijing Olympic Games was successfully held in these stadiums coated
with polyurea elastomer.
|


|